January 9, 2009 – Six months after a fire destroyed Washburn & Doughty’s main construction building, the company is beginning the year with steady progress on the new building. Sheridan Construction began hanging siding on the East Bay this week and by Friday the east wall was about 50% complete. A summary of progress on the East Bay is as follows:
• The concrete floor has been poured, with grounding straps in critical areas.
• Vertical columns are erected.
• The roof is complete.
• (2) Twenty-Ton Cranes have been installed.